To plan rooftop solar, check your electricity bills and your roof, size the system from your daily units, pick the right system type, set a budget with subsidy, choose a reliable installer and complete the DISCOM approvals. A little planning before you buy prevents most problems later.
This guide walks through each planning step, with a simple sizing table you can use before you talk to an installer.
Divide your daily units by the 4 to 5 units that 1 kW of solar often produces per day in a sunny part of India. The table below shows approximate sizes. They are a guide, and your installer will refine them for your site.
| Monthly bill (units) | Daily use (units) | Approx. system size | Roof space needed |
|---|---|---|---|
| 150 | About 5 | 1 to 1.5 kW | About 10 to 15 sq m |
| 300 | About 10 | 2 to 2.5 kW | About 20 to 25 sq m |
| 450 | About 15 | 3 to 3.5 kW | About 30 to 35 sq m |
| 600 | About 20 | 4 to 5 kW | About 40 to 50 sq m |
Remember that the central subsidy is capped at 3 kW. A larger system is possible, but the extra capacity does not get extra subsidy. Read the PM Surya Ghar Yojana guide for the application process.
| If your situation is... | Plan for... |
|---|---|
| Reliable grid, goal is lower bills | On-grid solar with net metering |
| Frequent power cuts, need backup | Hybrid solar with battery |
| No grid or very remote site | Off-grid solar with a battery bank |
Working back from official subsidy figures, benchmark costs are roughly Rs 50,000 for 1 kW, Rs 1 lakh for 2 kW and Rs 1.45 lakh for 3 kW before subsidy. These are estimates, and real quotes vary with brand, roof and location. Our solar panel cost in India guide explains how to compare quotes and estimate payback.
Installation itself is usually quick once approvals are in place, but the full process, including DISCOM approval, inspection and net meter installation, can take several weeks and varies by state. Start early, especially if you want to use the subsidy before the scheme's FY 2026-27 timeline ends. After installation, follow our maintenance guide to protect output, and read how solar panels work if you want the basics.
| Roof type | Typical mounting | Points to check |
|---|---|---|
| Flat concrete (RCC) | Tilted structures on the roof, usually with concrete footings or clamps | Waterproofing, parapet height, shade between rows |
| Sloped metal sheet | Rail or clamp systems fixed to the sheet | Sheet condition, fastening strength, leak sealing |
| Tiled roof | Hooks fitted under or between tiles | Tile condition, roof framing strength |
| Ground or elevated structure | Raised structure over open space or parking | Space, cost and foundation needs |
Visit your roof at around 9 am, noon and 3 pm, and note shadows from tanks, walls, trees and nearby buildings. Remember that the sun sits lower in winter, so shadows are longer than in summer. Photograph each shadow position, or ask your installer to run a shade analysis. Place panels on the area that stays clear for the longest part of the day.
| Item | Why it matters |
|---|---|
| DISCOM application and approval | Needed for grid connection and net metering |
| Subsidy registration on the national portal (homes) | Needed to claim the central subsidy |
| Owner consent or society permission | Required if the roof is shared or the building is a society |
| Net meter installation and commissioning | Starts exports and billing credit |
| Invoice, warranty and commissioning documents | Needed for claims, service and records |
Our PM Surya Ghar Yojana guide explains the subsidy process stage by stage.
You can install solar at any time of year, but the monsoon can slow roof work and delay inspections. Many people start planning in the dry season so the system is live before the high-generation months. Given that the central scheme is set to run until FY 2026-27, avoid leaving your application to the last minute.
Good rooftop solar planning comes down to four things: know your consumption, check your roof, choose the right system type and compare clear quotes. Do these first and the rest of the process becomes much simpler.
Ready to plan yours? Contact a certified solar installer for a free site assessment and a system size recommendation based on your bills.
Collect your electricity bills, assess your roof, decide your goal, choose the system type, size the system, set a budget with subsidy, compare quotes and complete the approvals.
As a rough guide, you need about 10 square metres, or around 100 sq ft, of shadow-free roof for each kW of solar.
Divide your daily electricity units by the 4 to 5 units that 1 kW often generates per day in a sunny part of India. A home using about 10 units a day typically needs roughly 2 to 2.5 kW.
South-facing panels tilted close to your city's latitude usually capture the most energy, though your installer may adjust the design for your roof.
Shade can reduce output noticeably. Your installer can check shadows through the day and suggest placement, panel layout or a different position to limit the loss.
Yes, you need your DISCOM's approval, and the system must be inspected and commissioned. For the central subsidy you must also follow the national portal process.
The physical installation is usually quick, but approvals, inspection and net meter installation can take several weeks and vary by state and DISCOM.
Choose on-grid if your power supply is reliable and you want the quickest payback, hybrid if outages are frequent, and off-grid only where no dependable grid exists.
Visit the roof at about 9 am, noon and 3 pm, note the shadows from tanks, walls and trees, and remember that winter shadows are longer. Your installer can also do a shade analysis.
Yes. Tiled and sheet roofs use special mounting hooks or rails. The installer must check the roof's condition and strength first.
If you expect higher consumption soon, size the system for it or leave roof space and capacity to expand later.
Keep your electricity bill, ID proof, roof ownership proof and bank details ready. Societies may also need permission from the managing body.